LPK08-801 » Details
| Status: | Contact: | ||
| Status | MAG Manager | ADOT Manager | Agency Manager |
| Active | Eileen Yazzie eyazzie@mag.maricopa.gov |
John Dickson None |
Paul Gilmore None |
| Programming: | |
| TIP ID Number | Location |
| LPK08-801 | Various locations |
| Work Description |
| Pave unpaved alleys |
| Modal Type | Fiscal Year | Federal Source | Federal Cost | Regional Cost | Local Cost | Total Cost |
| AQ or TDM | 2009 | CMAQ | $530,979 | $0 | $227,562 | $758,541 |
| Design Review and Clearance Status | ||||
| Tracs Number | Federal Number | Bid Date | Bid Amount | Project Closed Out |
| SS 666 01C | CM-LPK-0(200)A | |||
| Design Concept Report: | Environ. Clearance: | Right-of-Way Clearance: | Utilities Clearance: | Design Status: |
| Approved 2007-12-01T00:00:00 |
| History: | Supplemental Information : |
| 12/08/08 ADOT Local Governement: A draft environmental clearance has been submitted. |