GLB06-203B » Details

Status: Contact:
Status MAG Manager ADOT Manager Agency Manager
Authorized Eileen Yazzie
eyazzie@mag.maricopa.gov
Bill Snarr
None
Rick Hooker
None
Programming:
TIP ID Number Location
GLB06-203B Gilbert Town Center
Work Description
Design traffic management center (phase B) and purchase further equipment
Modal Type Fiscal Year Federal Source Federal Cost Regional Cost Local Cost Total Cost
ITS 2007 CMAQ $368,401 $0 $126,599 $495,000
Design Review and Clearance Status
Tracs Number Federal Number Bid Date Bid Amount Project Closed Out
SS 637 01C  CM-GLB-0(200)A       
Design Concept Report: Environ. Clearance: Right-of-Way Clearance: Utilities Clearance: Design Status:
 2007-08-01T00:00:00  2007-08-01T00:00:00  2007-08-01T00:00:00  2007-08-01T00:00:00  2007-08-01T00:00:00
History: Supplemental Information :
  Procurement project - does not involve earth disturbance.