GDY04-204C » Details

Status: Contact:
Status MAG Manager ADOT Manager Agency Manager
Authorized Eileen Yazzie
eyazzie@mag.maricopa.gov
Bill Snarr
None
Luke Albert
None
Programming:
TIP ID Number Location
GDY04-204C Litchfield Rd: Wigwam Blvd to MC 85
Work Description
Install conduit and fiber cabling (smart corridor)
Modal Type Fiscal Year Federal Source Federal Cost Regional Cost Local Cost Total Cost
ITS 2007 CMAQ $902,440 $0 $125,000 $1,027,440
Design Review and Clearance Status
Tracs Number Federal Number Bid Date Bid Amount Project Closed Out
SS 507 01C  CM-GDY-0(007)A       
Design Concept Report: Environ. Clearance: Right-of-Way Clearance: Utilities Clearance: Design Status:
Approved 5/04 2004-05-04T00:00:00 Approved 10/04 2004-10-04T00:00:00     Plans at 100% 2007-08-01T00:00:00
History: Supplemental Information :
No change in 04-07 TIP, 8/3/03. No change, Errata Sheet 03-1, 3/26/02. Reported underway in 03-07 TIP, 1/21/02. Added to 04, partially replaces GDY04-204 (see also GDY04-204D in 01), Errata Sheet 02-4, 5/23/01.  Project not expected to be authorized in 2007