CHN07-302C » Details

Status: Contact:
Status MAG Manager ADOT Manager Agency Manager
Authorized Eileen Yazzie
eyazzie@mag.maricopa.gov
Adel Edward
None
Paul Young
None
Programming:
TIP ID Number Location
CHN07-302C Dobson Rd at Warner Rd (phase 1 of 2)
Work Description
Construct dual left turns and add auxiliary lanes in all directions
Modal Type Fiscal Year Federal Source Federal Cost Regional Cost Local Cost Total Cost
Street 2008 CMAQ $3,000,000 $0 $5,516,000 $8,516,000
Design Review and Clearance Status
Tracs Number Federal Number Bid Date Bid Amount Project Closed Out
SS 549 03D & 01C  CM-CHN-0(025)A       
Design Concept Report: Environ. Clearance: Right-of-Way Clearance: Utilities Clearance: Design Status:
Approved 07 2006-02-01T00:00:00 Approved 07 2006-09-01T00:00:00 Approved  Approved  Approved 3/08 2008-03-01T00:00:00
History: Supplemental Information :
No change in 04-07 TIP, 8/1/03. Added to 07 with $3,000,000 CMAQ as part of FY03 close out (replaces CHN07-302 as construction phase - see also CHN07-302D in 03) in TIP Amendment 03-8, 6/25/03.  The project has been Authorize