Local Sponsored Federal Project Timeline

 

Construction projects can complete the ADOT administered federal design and clearance process in 18 to 24 months.  The chart below is for a user to get an approximate schedule for their project once the initial start date is entered. Use the pull-down menus to select your start dates, then click "Change Dates."

Anticipated Milestones
The following project milestones are based on a typical project procurement process. Some projects may follow abbreviated process. Please indicate (yes/no) the applicable milestones.

Standard Milestones Months Applicable
Milestones

Estimated Begin Date

Apply for ADOT project number 0 Y- N Sept-2007
Receipt of ADOT project number 1 Y- N Oct-2007
Initial DCR 4 Y- N Jan-2008
Final DCR 5 Y- N Feb-2008
30% Preliminary Plans, Cost Estimate and Report 7 Y- N Apr-2008
60% Preliminary Plans, Cost Estimate and Report 9 Y- N Jun-2008
Final Preliminary Plans, Cost Estimate and Report 11 Y- N Aug-2008
Environmental Clearance 9 Y- N Jun-2008
Utility Clearance 10 Y- N Jul-2008
Right-of-Way Clearance 10 Y- N Jul-2008
PS&E Approval 15 Y- N Dec-2008
Bid opening 18 Y- N Mar-2009
Final Deployment 24 Y- N Sept-2009

To obligate a federally funded project, the project sponsor must have a bid ready project and a complete set of clearances – environmental, right-of-way and utilities. As the federal fiscal year effectively ends in mid September, sponsors of construction projects should meet these two milestones to reach obligation for that current federal fiscal year: